Worked example
A 12 m² floor with 10% waste requires 13.2 m² of flooring. At 2 m² per pack, round up to seven packs. Concrete volume for 4 m by 3 m by 0.1 m is 1.2 m³ before allowance.
Before using the result
Check actual product coverage, pack sizes, site measurements and supplier recommendations. The tool does not determine structural thickness, safe quantities or suitability. Use the cost estimators for project budgets and the job description generator to record scope.